Smart City Mission
Project delivery and PMIS exception view retained as a supporting route.
Open cases
Department-relevant case state
Sector 56-61 utility strain and roadworks grievance cluster
Grievances on low voltage, water strain, and trench restoration are converging around active roadworks and utility pressure.
Madhya Marg corridor milestone and vendor exception risk
A Smart City corridor package has slipped on milestone delivery while payment progression and complaint risk are both rising.
Urgency by case
Supporting analytics
Recent source signals
Department feed excerpts
Payment progress outpacing delivery on package 07
Payment progression is at 72 percent while the package is still carrying an unresolved milestone slip and repeat-vendor history.
Restoration milestone slipped on utility trench package
The restoration milestone attached to utility trenching in Sectors 56 to 61 slipped by four days and is now impacting public complaints.
Madhya Marg package 07 milestone slip
Package 07 on the Madhya Marg corridor has slipped by nine days against the published milestone sequence.